- Budget 2027 revealed an additional €6bn for Dublin’s MetroLink project
- The funding will be spent between 2027 and 2030
- The estimated total cost of the MetroLink project ranges from €14.4bn to €17.5bn
- Work on the ground is expected to begin next year
- Operations are expected to begin between 2036 and 2038
Minister for Public Expenditure Jack Chambers has revealed an additional €6bn for Dublin’s MetroLink project as part of Budget 2027. The funding will be spent between 2027 and 2030. The estimated total cost of the MetroLink project ranges from €14.4bn to €17.5bn with the expected centre point of €15.75bn. Work on the ground for MetroLink is expected to begin next year with a view to operations beginning in about 10 to 12 years time between 2036 and 2038.
The additional €6bn funding will be spent between 2027 and 2030. The estimated total cost of the MetroLink project ranges from €14.4bn to €17.5bn. Work on the ground is expected to begin next year.
The MetroLink project will receive an additional €6bn in funding. The funding will be spent between 2027 and 2030. Operations are expected to begin between 2036 and 2038.